Automatically Assigning Individual Sequence Calls
Note |
|---|
This topic applies only to SWCs specified as block diagrams. |
You can edit individual normal or block-local sequence calls, empty or assigned, simply and quickly as follows:
In the Outline tab, select the method or process to which the sequence call is to be assigned.
If you do not select a method or process, the sequence call is assigned to the default method/runnable.
Note
For a block-local sequence call, this selection is irrelevant. A block-local sequence call is always assigned to its statement block.
Do one of the following:
- In the drawing area, double-click the sequence call you want to edit.
Right-click the sequence call and select Next Number from the context menu.
Note
If no method/runnable has been selected, the system uses the method/runnable most recently assigned to a sequence call.
The selected method/runnable as well as the next free number are assigned to the sequence call.
The
following rules apply here, in using the values for Sequence Step Size and Use gaps set in the ASCET option window.
See also
Editing a Sequence Call in the Sequence Editor
Incrementing/Decrementing Individual Sequence Calls
Resetting an Individual Sequence Call