Deassigning a Process from a Task
- In the project editor, go to the "OS" tab.
- In the Tasks pane, select the process you want to deassign.
Do one of the following:
In the Task menu, select Deassign Processes.
Click the << button.
Select Deassign Processes from the context menu.
Drag the process from the Tasks pane into the Processes pane.
The process is removed from the current task.