Defining the Scheduling of Continuous Time Blocks

  1. In the project editor, go to the "OS" tab.
  2. Select a CT task in the Tasks pane.
  3. Adjust the settings for trigger mode etc. as necessary.

You can now experiment with the hybrid project in the same way as with a project containing only modules. In the experimentation environment a solver has to be assigned to each continuous time block. Different solvers can be assigned to blocks within the same project, which means that multi-rate experiments are possible. Assigning solvers is described in Experimenting with Continuous Time Blocks.

See also

Experimenting with Continuous Time Blocks